viii SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Related DocumentationThe latest versions of all the SPARC Enterprise Seri
Preface ixSPARC Enterprise T5120 andT5220 Servers Service ManualHow to run diagnostics to troubleshoot theserver, and how to remove and replaceparts i
x SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Note – Product Notes are available on the website only. Please check for the
1SPARC Enterprise T5120 and T5220Servers Site Planning GuideThis guide provides specifications and site planning requirements for the SPARCEnterprise
2 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Physical SpecificationsRelated Information “Minimum Clearance for Service A
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 3Minimum Clearance for Service AccessRelated Information “Environmental Specifications”
4 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Environmental SpecificationsRelated Information “Power Source Requirements”
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 5Power Source RequirementsBoth the SPARC Enterprise T5120 and T5220 servers have two auto
6 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009TABLE 6 SPARC Enterprise T5120 Server (8-Disk Capable) Power SpecificationsG
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 7Maximum Server Configuration SpecificationsUnder Nominal Temperature and Voltage Conditi
8 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Note – The maximum operating input current values are based on P / (V * 0.95
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 9Agency Compliance SpecificationsRefer to the SPARC Enterprise T5120 and T5220 Servers Sa
10 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009Electrical PowerGood practice is to connect each power supply to a separate
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 11Related Information “Ambient Relative Humidity” on page 10Airflow Considerations Ensu
12 SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009
SPARC EnterpriseTMT5120 andT5220 Servers Site Planning GuidePart No. 875-4190-12July 2009, Revision AManual Code C120-H027-03EN
PleaseRecycleCopyright © 2009 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, California 95054, U.S.A. All rights reserved.FUJITSU LIMITED p
Copyright © 2009 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, California 95054, Etats-Unis. Tous droits réservés.Entrée et revue tecnical
vContentsPreface viiSPARC Enterprise T5120 and T5220 Servers Site Planning Guide 1Physical Specifications 2Minimum Clearance for Service Access 3Envir
vi SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009
viiPrefaceThis guide provides the specifications and site requirements you need when planningthe installation of the SPARC Enterprise™ T5120 and T5220